What a FAT Is, and What It Is Not
A factory acceptance test (FAT) is the formal acceptance of the machine at the supplier's factory, before it ships. It is not the same as a packaging test.
| Packaging test | FAT | |
|---|---|---|
| When | Before you order | Before the machine ships |
| Configuration | The machine chosen for your package, adjusted during the test | The final configuration agreed for the project |
| What it checks | Whether your product and package run well, and what needs to change | The machine against acceptance criteria agreed in advance |
| Result | A recommendation to proceed, adjust or retest | Acceptance, with stops and open items recorded |
The packaging test answers "can this work?". The FAT answers "does this machine do what we agreed?". A useful habit: record the packaging test result and use it as the output target at FAT.
Before the FAT: Agree These in Writing
Criteria are agreed before the result is known, not adjusted afterwards to fit it. Put these in writing before the build is finished:
- ☐ Product and its condition, as it will run on your line
- ☐ Package: bag, pouch or tray, film or material, and fill weight
- ☐ Machine configuration and options
- ☐ Tooling and forming set for each bag or tray size
- ☐ Software version, where relevant
- ☐ Target good output, in accepted packs per hour
- ☐ Acceptance criteria: what the machine must reach, and how each item is measured
- ☐ FAT duration and scope: it depends on the project and the acceptance scope, so agree it together with the criteria
For a complete line, add:
- ☐ The modules in the line, and who is responsible for each one
- ☐ Mechanical and electrical interfaces between modules
- ☐ Product, pack, case and pallet flow
- ☐ The line bottleneck
- ☐ What the FAT covers, and what is left for commissioning at your site
If your product or package changes after this point, review the effect on the criteria before the test, not during it.
The Factory Acceptance Test Checklist
Use this list on the day. Not every item applies to every project; mark the ones that do not as not applicable instead of deleting them.
Configuration and build
- ☐ The machine matches the written configuration: model, options, tooling and software version
- ☐ Each function has been checked before any product runs
- ☐ Alarm and safety checks: emergency stops, guards and interlocks stop the machine as they should
Running your product
- ☐ The test runs with your product and package material, not a substitute, unless agreed
- ☐ Good output: accepted finished packs per hour over the agreed run
- ☐ Fill weight against the agreed limits
- ☐ Seal and closure quality: no product in the seal, no leaks on the agreed check
- ☐ Package dimensions and appearance
- ☐ Residual O₂ or cap torque, where they apply
- ☐ Inspection and reject tests: checkweigher or metal detector rejects test packs as agreed
- ☐ Yield: rejects and product losses counted
- ☐ Changeover to a second bag size or product, if it is part of the criteria
- ☐ Case packing and palletizing, where included
Stops
Record every stop by cause, instead of one total. Typical causes:
- ☐ Product starvation
- ☐ Film, pouch or cap supply
- ☐ Jam or blockage
- ☐ Packaging machine fault
- ☐ Fault on other line equipment
- ☐ Operator intervention
- ☐ Planned changeover
- ☐ Site utilities
- ☐ Safety stop
Documents and handover
- ☐ Installation guide and maintenance manual
- ☐ Wear parts supplied with the machine, and the recommended spare parts list
- ☐ The recorded configuration, including software version and tooling
- ☐ The FAT record and the open-item list
How to Count Output at FAT
Machine cycles show how fast the machine moves. Acceptance should count the packs you can sell:
Good output = accepted finished packs per hour
That means rejects, empty bags, underweight packs and packs with product in the seal are left out, and the stops above are counted against the run. A quote based only on the machine maximum is not an acceptance figure. What Determines Actual VFFS Packaging Speed? explains why the two numbers differ.
Reading the Result
Each criterion should end with one of four results, written down:
- Pass: all agreed criteria are met.
- Pass with open items: accepted, with the open items recorded for closing.
- Retest required: a criterion is not met; the machine is adjusted and the test is repeated.
- Not tested: a criterion that could not be tested, recorded as such.
"Not tested" is not the same as passed. If something could not be tested at the factory, such as a link to equipment you supply yourself, move it to the commissioning plan at your site.
After the FAT: Commissioning at Your Site
FAT happens at the supplier's factory. The machine is then installed and commissioned at your site, where the remaining checks happen with your utilities, your other equipment and your operators:
- ☐ Site readiness and utilities confirmed: power, compressed air, space
- ☐ Machine installed and connected within the agreed responsibility
- ☐ Interfaces with other line equipment checked
- ☐ Your product and package run under production conditions, where included
- ☐ Open items from the FAT and from commissioning closed
- ☐ Operation and maintenance handed over to your team
With us, the installation guide and maintenance manual come free with every machine. Our engineers can install on site at your cost, or guide your team by video call free of charge; see Installation & Commissioning.
Attending the FAT
Every machine we build is tested before it leaves our factory. You do not have to travel: where the project includes it, you can attend at our factory in Hebei or follow the FAT on a live video call, and you receive the test records and video. If you join remotely, ask for the camera to show the counters, the reject bin and the HMI alarm list, not just the running machine.
Questions to Ask Any Supplier
- Which acceptance criteria will be written down before the build, and who signs them?
- Is output counted as accepted packs per hour, or as machine cycles?
- Will the FAT run with my product and package material?
- How are stops recorded, and by which causes?
- Which results are possible, and what happens if a criterion fails?
- Can I attend in person or by live video call?
- What is checked at FAT, and what is left for commissioning at my site?
FAQ
What is a factory acceptance test for a packaging machine?
It is the formal check, at the supplier's factory and before shipping, that the machine meets acceptance criteria agreed in advance: output, fill weight, seal quality and the other items in your contract.
How is FAT different from a packaging test?
A packaging test happens before you order and checks whether your product and package can run well. FAT happens before the machine ships and checks the final configuration against written criteria.
Can I attend the FAT remotely?
Often, yes. Ask the supplier for a live video call, and agree in advance which counters, rejects and alarms the camera will show.
What happens if the machine does not meet a criterion?
The result is recorded as "retest required". The machine is adjusted and that part of the test is repeated. Items that are accepted but not finished are recorded as open items. Ask for each open item to be recorded with who closes it and a target date.